Task name: Reconstruction of the railway flyover at the line no. 137 at km 23.126 – Design and build.
Investor: PKP PLK S.A. Zakład Linii Kolejowych w Tarnowskich Górach
General Contractor: Nowak-Mosty Sp. z o.o.
Structure’s technical parameters:
Construction on the track of the line no. 147 Zabrze Biskupice – Gliwice – 2 pcs.
Structure: single-span truss, closed at the top, with traffic allowed on bridge sleepers
Total length: Lc = 32.90 m
Theoretical span length: Lt = 32.0 m
Obstacle(s): track 1 and track 2 on the line no. 200 Gliwice – Gliwice Sośnica
Construction on the track of the line no. 711 Gliwice – Maciejów Północny – 1 pcs.
Structure: single-span truss, closed at the top, with traffic allowed on bridge sleepers
Total length: Lc = 40.80 m
Theoretical span length: Lt = 40.0 m
Obstacle(s): track 1 and track 2 on the line no. 200 Gliwice – Gliwice Sośnica
Scope regarding bridge and track industries:
The structure is located in the line of the railway line no. 137 Katowice – Legnica, a national-level primary/central double-track electrified line.
Delivery time: start date: 29/06/2017; end date: 30/11/2017