Task name: Improvement of accessibility to the junctions at the A4 motorway between Gogolin and Olszowa. Expansion of the voivodeship road no. 426 at the section Piotrówka – Zawadzkie, from km 0+188 to km 7+896.
Investor: Voivodeship Road Management Board in Opole
General Contractor: DROG-BUD Sp. z o.o.
Qualified Subcontractor Nowak-Mosty Sp. z o.o.
Scope regarding bridge industry:
- Demolition of the existing one and construction of a road bridge at km 2+023.00 across the Mostki River, monolithic framework, Lt = 5.60 m, Lc = 11.40 m.
- Demolition of the existing one and construction of a road bridge at km 2+420.50 across the Bziczka River, monolithic framework, Lt = 5.60 m, Lc = 11.40 m.
- Demolition of the existing ones and construction of new culvers made of prefabricated box-shaped components at km 1+073.00 and 1+722.00 and 6+602.00, total length Lc = 37.0 m.
Delivery time: start date: 01/09/2016; end date: 2016