Task name: Construction of a ring road for Woźniki.
Contracting Party: Voivodeship Road Management Board in Katowice
General Contractor: Consultation: Drog-Bud Sp. z o.o./Nowak-Mosty sp. z o.o.
Technical parameters:
Class G voivodeship road with supporting infrastructure.
Scope:
- Construction of Class G voivodeship road, from km 0+000 to km 4+480.61, excluding the section of a slip road at the Woźniki junction (from km 1+187.63 to km 1+595.52)
- Construction of road junctions, including: construction of a roundabout at the DW 789 junction – km 0+000 – Roundabout 1; construction of a roundabout at the junction with the Woźniki junction slip road – km 1+124.92 – Roundabout 2; expansion of the roundabout at the junction with the DP 2336S slip road (addition of the Eastern access road) – km 1+595.52 – Rounadabout 3; construction of the DG 635017S junction – km 3+727.43, construction of a roundabout at the DW 789 junction – km 4+480.61 – Roundabout 4.
- Construction of traffic control facilities and vehicle weighing facilities.
- Construction of roads allowing access from areas adjacent to the ring road’s right-of-way area.
- Construction of road drainage (road ditches, road sewage), construction of culverts.
- Construction and reconstruction of technical infrastructure, including construction of a rainwater sewage system;
- Reconstruction of a water supply system, reconstruction of a gas supply system
- Construction of a street lighting system, reconstruction of a power distribution system;
- Reconstruction of a telecommunications network;
- Construction of a service duct;
- Cutting of trees and bushes;
- Construction of road safety equipment;
- Construction of the passage for access road – PG-01:
– load class A + special vehicle class 150 (Stanag 2021)
– closed reinforced concrete framework
– total length Lc = 15.5 m
– theoretical span length – Lt= 3.90 m (vertical clearance gauges 3.5 m)
Delivery time: start date: 23/09/2017; end date: 30/11/2018