Task name: Complete construction of a flying junction over the national line no. DK 94 with equipment in the km range of: 0+150 to 0+306.
Investor: Leroy-Merlin Inwestycje Sp. z o.o.
General Contractor: Hochtief Polska S.A.
Qualified Subcontractor: Nowak-Mosty Sp. z o.o.
Scope regarding bridge industry:
– temporary rearrangement of vehicle traffic and its maintenance.
– completion of piles with test loading
– completion of reinforced concrete works for the supports, load-bearing structure and passage plates
– completion of insulation and drainage
– installation of relevant equipment
– construction of escarpments made of reinforced soil
– test loading
Structure’s technical parameters:
Pre-stressed girder-based load-bearing structure, connected with crosswise beams, composited with reinforced concrete deck plate.
Obstacle(s): DK 94
Delivery time: start date: 16/07/2018; end date: 31/08/2019