Task name: Revitalisation of the railway line no. 292 – bridge industry – Design and build.
Investor: PKP Polskie Linie Kolejowe S.A.
General Contractor: ETF Polska Sp. z o.o.
Qualified Subcontractor Nowak-Mosty Sp. z o.o.
Scope regarding bridge industry:
– culverts – 27 pcs.
– flyovers – 1 pcs.
– bridges – 1 pcs.
Revitalisation of the aforementioned structures includes:
– renovation of supports with addition of anti-corrosion protection;
– construction of sills and wings;
– repair of insulation and drainage;
– addition of anti-corrosion protection to steel structures;
– adjustment of handrails to applicable laws;
– re-profiling and reinforcement of embankment cones.
The engineering structures are located in the line of the railway line no. 292 Jelcz Miłoszyce – Wrocław Osobowa at the section Jelcz Miłoszyce – Wrocław Sołtysowice, a local-level single-track non-electrified line.
Delivery time: start date: 26/02/2019; end date: 20/11/2019