Task name: Reconstruction of the railway flyover at km 8.957 at the line Łódź Widzew – Kutno over Łagiewnicka street in Łódź – Build.
Investor: PKP PLK S.A. Zakład Linii Kolejowych w Łodzi
Contractor: Nowak-Mosty Sp. z o.o.
Technical parameters of the new structure:
Scope regarding bridge industry:
– demolition of the existing load-bearing structure with equipment
– construction of a new load-bearing structure, retaining existing geometrical parameters (length and width)
– adaptation of lower bossage and gravel wall on the abutment
– replacement of balustrades on the load-bearing structure and the abutments
– replacement of the service stairs
– repair of reinforcement of the abutment cones
The structure is located in the line of the railway line no. 016 Łódź Widzew – Kutno, a national-level primary single-track electrified line.
Delivery time: start date: 26/05/2017; end date: 16/10/2017