Task name: Renovation of the bridge in the line of DK 11 in Kostów – Build.
Contracting Party: Generalna Dyrekcja Dróg Krajowych i Autostrad w Opolu
General Contractor: Nowak-Mosty Sp. z o.o.
Structure’s technical parameters:
Scope:
– rearrangement of vehicle traffic (alternating traffic)
– demolition of existing road surface
– demolition of equipment components
– disassembly of the insulation’s protective concrete
– completion of slope layer
– completion of insulation
– injection of fractures
– re-profiling of concrete surfaces of spans
– anti-corrosion protection for concrete surfaces
– completion of new footway surfaces with equipment
– reinforcement of escarpment cones and stairs
– completion of a new road surface on the bridge and its access roads
Delivery time: start date: 15/04/2019; end date: 26/09/2019